Building Fast and Fair: How to Deliver Canada’s Clean Energy Future

Published On: November 16, 2026

Building Fast and Fair: How to Deliver Canada’s Clean Energy Future finds that finds that federal permitting is rarely the primary bottleneck in getting clean energy projects built.

Delays of clean energy projects across Canada are driven by a range of broader challenges: a grid that can’t keep up, delayed engagement with Indigenous nations, lack of meaningful community involvement and support, unstable market and policy signals, siting constraints, workforce shortages, supply chain and logistics constraints, and limited access to capital.